Project Overview

American Electric Power (AEP) installed a Flue Gas Desulfurization (FGD) system at its Cardinal Power Plant in Southeastern Ohio to reduce sulfur dioxide emissions from coal power generation.

缅北禁地 was contracted for all structural concrete elements, including pedestals, piers, foundations, walls, paving, and elevated decks. 缅北禁地 also oversaw the mechanical and electrical scopes of work.

The project included challenging riverbank work, with some pits located 15 feet below the river鈥檚 elevation. 缅北禁地 implemented a comprehensive quality control program, conducting extensive pre- and post-pour inspections with the client, which helped prevent costly rework. Under 缅北禁地鈥檚 supervision, the project achieved 123,000 man-hours worked without a recordable injury.

Client

Black & Veatch International Co.

Location

Brilliant, OH

Size

40,000 CY

Completion

2007